Planned Road Works
Please find planned road works within the Melton Asfordby Division in the table below:
| Road Name/Number & Location | Description | Estimated Start Date | Estimated End Date | Traffic Management |
| Leicester Road | Melton Mowbray | Replacement of Railway Bridge and more | 23/08/10 | 30/03/11 | Road closure and 20mph speed limit. Please see notice, map 1 & map 2 |
| Hickling Ln | Nether Broughton | Kerbing & drainage | 04/10/10 | 31/12/10 | Diversion, see press release & map |
| PROW H38 | Kirby Bellars | Newt Collection | 04/10/10 | 04/04/11 | Closure & diversion of footpath, notice & plan |
| Shoby Bends | Asfordby | Road widening | 01/11/10 | 01/11/10 | 30mph speed limit, see press release & map |
| Main St | Kirby Bellars | Bridge replacement | 04/12/10 | 16/01/11 | Closure, see press release & map |
| Main St Railway Bridge | Kirby Bellars | Dismantling and re-erecting of railway bridge | 22hrs 04/12/10 | 13hrs 05/12/10 | Closure but no diversion |
| 22hrs 11/12/10 | 13hrs 12/12/10 | |||
| 22hrs 18/12/10 | 13hrs 19/12/10 | |||
| 22hrs 08/01/11 | 13hrs 09/01/11 | |||
| 22hrs 15/01/11 | 13hrs 16/01/11 | |||
| 22hrs 23/01/11 | 13hrs 23/01/11 |
New Chevron boards and verge marker posts were installed in Burton Lazars and completed on the 13th April 2010.
|
|
|
A new gate was put in on Asfordby Hill and finished on 16th July 2010
|
|
LCC are proposing to realign the kerbs outside 2 Main Rd, Twyford as the property has been hit a number of times by vehicles turning into Ashby Rd. The temporary arrangements will be in place for a few days after which LCC propose to order the works for construction. Click here for a picture
An update on the works at Wood Hill, Old Dalby
The long delayed works at Wood Hill will commence its first phase next Tuesday with boreholes being taken at intervals up the slope. This work is scheduled to last from Tuesday until the following Wednesday (weather permitting). Temporary lights will be in place during this period to allow the contractor to work safely.
This is just the prelude to the main sheet-piling work. The boreholes will need to be be analysed by a soils lab in order that the sheet-piling contractor can properly design the sheet pile proposal and identify the correct machinery to sucessfully drive the piles. This means that there will be an interval between next week’s borehole work and the further sheet-piling phase. A definite timescale can’t be given but it is likely that the sheet-piling will not commence until just after Christmas.